Basis for Recommendation
The train simulator was not updated to the new signal arrangement for the DCCR Project, as a result, the RAIU make the following safety recommendation:
back to recommendations listing
Ref # | 2023001-07 |
---|---|
Status | Further Evidence Requested |
Occurrence | Dangerous occurrence involving a Double SPAD at Clontarf Road Station, 7th December 2021 |
Occurrence Date | 07 December 2021 |
The train simulator was not updated to the new signal arrangement for the DCCR Project, as a result, the RAIU make the following safety recommendation:
IÉ-IM SET should put systems in place to ensure that the train simulator staff are provided with updated signal layout schematics as and when required e.g. altered signal positions.